Eavor Technologies is delivering electricity to the German grid from its Geretsried geothermal project, though the company is revising its expansion timeline following significant engineering challenges during the construction of its first loop.

Chips & Climate Desk
Updated Nov 9, 2026 3 min read
Eavor's Closed-Loop Geothermal System Begins Grid Power Delivery in Germany

Eavor Technologies has been delivering electricity to the German grid from its Geretsried facility since late last year, according to Canary Media. The project, which utilizes a closed-loop geothermal design, has completed the first of four planned loops. While the system is currently operational, it is producing approximately half a megawatt of power. This output represents a proof-of-concept for the technology rather than the full-scale capacity, which the company intends to eventually reach at 8.2 megawatts of electricity or 64 megawatts of district heating for nearby municipalities.

The path to this initial grid connection was marked by significant engineering hurdles. Canary Media reports that Eavor encountered unstable boreholes, equipment failures, and slow drilling speeds while working deep underground. The company initially attempted to use two drilling rigs in parallel to create motherbores for lateral wells, but poor cement casing allowed fluid and mud to circulate between the supposedly sealed rigs. To address this, the team switched to a single-rig approach, a temporary measure that increased both the time and cost required to complete the first loop.

Because of these complications, Eavor halted the first loop after completing six lateral well pairs instead of the planned 12. This decision allowed the company to refine its cementing design for future loops. Despite the setbacks, the company claims it has improved its operational efficiency. According to Canary Media, Eavor reported that by adapting its equipment and techniques—including the use of an active magnetic ranging system—it reduced average drilling times by over 70% between the first four lateral well pairs and the final ones. Matt Toews, Eavor’s co-founder and chief technology and operating officer, described the wells as moving from wet noodles to gun-barrel straight.

The company’s expansion plans are currently in flux. While Eavor previously expected to begin construction on its second loop earlier this spring, it is now revising that timeline. The startup is currently seeking new project partners and investors to assist with the next phase of development. Toews noted that the company is aiming to initiate the second loop as soon as practical, though the exact schedule remains uncertain. The project, which began drilling in July 2023, is supported by a grant from the European Union’s Innovation Fund.

The broader industry is watching Eavor’s progress as a test case for closed-loop geothermal, which aims to avoid the seismic risks and water consumption issues associated with traditional geothermal or enhanced geothermal systems. Emily Pope, a geologist and senior fellow at the Center for Climate and Energy Solutions, told Canary Media that the technical snags Eavor faced are understandable and predictable for a first-of-a-kind project. While closed-loop systems are generally considered less efficient at heat extraction than other methods because the working fluid does not make direct contact with the rock, they offer potential for deployment in regions where other geothermal methods are not viable.

The ultimate commercial viability of the Eavor-Loop design depends on the company's ability to scale. While the current output of half a megawatt confirms that the system can successfully extract heat, the project has yet to demonstrate the economics of full-scale operation. Future performance metrics, including the speed of subsequent loop construction and the ability to maintain consistent output, will determine if the technology can move beyond its current demonstration phase. As Eavor continues to navigate the learning curve of deep-well drilling, the industry remains focused on whether the company can successfully replicate its initial, albeit hard-won, success.